ANALISIS FAKTOR PENYEBAB KETERLAMBATAN PADA PEMBANGUNAN PROYEK “SCE” MENGGUNAKAN METODE ANALYTICAL HIERARCHY PROCESS

Authors

  • Rizki Prayudi Ramadhan

DOI:

https://doi.org/10.33086/bfj.v5i1.1489

Keywords:

Operastional Management, Project, Delay

Abstract

This study aims to identify and find solutions to delay construction work happening on the SCE project. The SCE project is a school building construction project. The background of this study is due to indications of delay with a difference of 25% between the schedule plan and the reality in the ground. The factors that cause the delay must be well identified so that a larger delay can be avoided and can provide solutions to these problems. From the results of Fishbone analysis and AHP, 11 factors were found to influence the delay in SCE project.

Downloads

Download data is not yet available.

References

Andi, Winata, S., Hendarlim, Y. (2005). Faktor-Faktor Penyebab Rework Pada Pekerjaan Konstruksi. Civil Engineering Dimension. 7(1):22-29..
Ladjao, J., Yurianto, E., Limanto, S., Wicaksono, E. (2016). Analisis Faktor Penyebab Keterlambatan Pada Bangunan Tinggi di Surabaya. Jurnal Dimensi Pratama Teknik Sipil. Vol. 5, No. 1.
Lastiyanti, Siwi D.D. (2015). Kajian Manajemen Resiko Sebagai Upaya Untuk Mencapai Keberhasilan Pada Proyek Konstruksi Baja dan Sipil di PT. Supra Surya Indonesia. Universitas Airlangga.
Le-Hoai, L., Lee, Y. D., Lee, J. Y. (2008). Delay and cost overruns in Vietnam large construction projects : A comparison with other selected countries. KSC Journal of Civil Engineering.
Lo, T.Y., Fung, I.W.H., Tung, K.C.F. (2006). Construction delays in Hong Kong civil engineering projects. Journal of Construction Engineering and Management. 132. pp.636-649.
Marzouk, M.M & El Rasas, T. (2013). Analysing Delay Causes in Egyptian Construction Projects. Journal of Advanced Research. Structural Engineering Department. Cairo University.
Moleong, Lexy. (2007). Metodologi Penelitian Kualitatif. Bandung: Rosdakarya.
Mubarak, S. (2005). Construction project scheduling and control. Pearson Prentice Hall.
Pujiyono, B. (2014). Konsep Manajemen Proyek. Universitas Terbuka. Jakarta. pp. 1-42.
Rahman, H. Abdul, Berawi, M.A., Berawi, A.R., Mohamed, O., Othman, M., Yahya, I.A.. (2006). Delay Mitigation in the Malaysian Construction Industry. Journal of Construction Engineering and Management. Vol.132. Issue 2.
Teguh, R. & Sudiadi. (2015). Manajemen Proyek. Available from http://eprints.mdp.ac.id.
Theodore J. Trauner, Mark F. Nagata, William A. Manginelli and Scott Lowe (2018), “Construction Delays (Third Edition)”

Downloads

Published

2020-04-14

How to Cite

Ramadhan, R. P. (2020). ANALISIS FAKTOR PENYEBAB KETERLAMBATAN PADA PEMBANGUNAN PROYEK “SCE” MENGGUNAKAN METODE ANALYTICAL HIERARCHY PROCESS. Business and Finance Journal, 5(1). https://doi.org/10.33086/bfj.v5i1.1489